Act No. 214
Public Acts of 2003
Approved by the Governor
December 1, 2003
Filed with the Secretary of State
December 2, 2003
EFFECTIVE DATE: December 2, 2003
STATE OF MICHIGAN
92ND LEGISLATURE
REGULAR SESSION OF 2003
Introduced by Reps. Palsrok, Gaffney, Taub, Wojno, Garfield, Brandenburg, Whitmer, Gillard, Nofs, Amos, Murphy, Farrah, Vagnozzi, Tabor, Rocca, Ward, Howell, Hopgood, Hune, Bisbee, Palmer, Farhat, Richardville, Kooiman, Minore, Newell, Rivet, Hoogendyk, Koetje, Stahl, Sak, Milosch, LaJoy, Acciavatti, Emmons, Shaffer, Robertson, Moolenaar, Drolet, Ruth Johnson, Condino, Elkins, Sheltrown, Hummel, Gieleghem, Accavitti, McConico, Casperson, Woronchak, Anderson, Stewart, Woodward, Phillips, Zelenko, Kolb, Spade, Lipsey, Voorhees, Middaugh, Meyer, Vander Veen, Adamini, Brown, Paletko, Pastor, Bieda, Gleason, Wenke, Byrum and Huizenga
ENROLLED HOUSE BILL No. 5188
AN ACT to amend 1939 PA 3, entitled "An act to provide for the regulation and control of public utilities and other services affected with a public interest within this state; to provide for alternative energy suppliers; to provide for licensing; to include municipally owned utilities and other providers of energy under certain provisions of this act; to create a public service commission and to prescribe and define its powers and duties; to abolish the Michigan public utilities commission and to confer the powers and duties vested by law on the public service commission; to provide for the continuance, transfer, and completion of certain matters and proceedings; to abolish automatic adjustment clauses; to prohibit certain rate increases without notice and hearing; to qualify residential energy conservation programs permitted under state law for certain federal exemption; to create a fund; to provide for a restructuring of the manner in which energy is provided in this state; to encourage the utilization of resource recovery facilities; to prohibit certain acts and practices of providers of energy; to allow for the securitization of stranded costs; to reduce rates; to provide for appeals; to provide appropriations; to declare the effect and purpose of this act; to prescribe remedies and penalties; and to repeal acts and parts of acts," by amending section 10a (MCL 460.10a), as added by 2000 PA 141.
The People of the State of Michigan enact:
Sec. 10a. (1) No later than January 1, 2002, the commission shall issue orders establishing the rates, terms, and conditions of service that allow all retail customers of an electric utility or provider to choose an alternative electric supplier. The orders shall provide for full recovery of a utility's net stranded costs and implementation costs as determined by the commission.
(2) The commission shall issue orders establishing a licensing procedure for all alternative electric suppliers. To ensure adequate service to customers in this state, the commission shall require that an alternative electric supplier maintain an office within this state, shall assure that an alternative electric supplier has the necessary financial, managerial, and technical capabilities, shall require that an alternative electric supplier maintain records which the commission considers necessary, and shall ensure an alternative electric supplier's accessibility to the commission, to consumers, and to electric utilities in this state. The commission also shall require alternative electric suppliers to agree that they will collect and remit to local units of government all applicable users, sales, and use taxes. An alternative electric supplier is not required to obtain any certificate, license, or authorization from the commission other than as required by this act.
(3) The commission shall issue orders to ensure that customers in this state are not switched to another supplier or billed for any services without the customer's consent.
(4) Within 180 days after June 5, 2000, the commission shall establish a code of conduct that shall apply to all electric utilities. The code of conduct shall include, but is not limited to, measures to prevent cross-subsidization, information sharing, and preferential treatment, between a utility's regulated and unregulated services, whether those services are provided by the utility or the utility's affiliated entities. The code of conduct established under this subsection shall also be applicable to electric utilities and alternative electric suppliers consistent with section 10, this section, and sections 10b through 10cc.
(5) Before December 31, 2003, the commission shall extend the temporary waiver for appliance service plans granted in case no. U-12134 issued February 20, 2003, to July 1, 2004, subject to the conditions imposed by that order. The enactment of this subsection shall not be deemed to prejudice, delay, or affect any pending legal case or legal proceeding.
(6) The orders issued by the commission before June 5, 2000 that allow customers of an electric utility to choose an alternative electric supplier, including orders that determine and authorize recovery of net stranded costs and implementation costs and that confirm any voluntary commitments of electric utilities, are in compliance with this act and enforceable by the commission. An electric utility that has not had voluntary commitments to provide customer choice previously approved by orders of the commission shall file a restructuring plan to allow customers to choose an alternative electric supplier no later than the date ordered by the commission. The plan shall propose a methodology to determine the electric utility's net stranded costs and implementation costs.
(7) This act does not prohibit or limit the right of a person to obtain self-service power and does not impose a transition, implementation, exit fee, or any other similar charge on self-service power. A person using self-service power is not an electric supplier, electric utility, or a person conducting an electric utility business. As used in this subsection, "self-service power" means any of the following:
(a) Electricity generated and consumed at an industrial site or contiguous industrial site or single commercial establishment or single residence without the use of an electric utility's transmission and distribution system.
(b) Electricity generated primarily by the use of by-product fuels, including waste water solids, which electricity is consumed as part of a contiguous facility, with the use of an electric utility's transmission and distribution system, but only if the point or points of receipt of the power within the facility are not greater than 3 miles distant from the point of generation.
(c) A site or facility with load existing on June 5, 2000 that is divided by an inland body of water or by a public highway, road, or street but that otherwise meets this definition meets the contiguous requirement of this subdivision regardless of whether self-service power was being generated on June 5, 2000.
(d) A commercial or industrial facility or single residence that meets the requirements of subdivision (a) or (b) meets this definition whether or not the generation facility is owned by an entity different from the owner of the commercial or industrial site or single residence.
(8) This act does not prohibit or limit the right of a person to engage in affiliate wheeling and does not impose a transition, implementation, exit fee, or any other similar charge on a person engaged in affiliate wheeling. As used in this section:
(a) "Affiliate" means a person or entity that directly, or indirectly through 1 or more intermediates, controls, is controlled by, or is under common control with another specified entity. As used in this subdivision, "control" means, whether through an ownership, beneficial, contractual, or equitable interest, the possession, directly or indirectly, of the power to direct or to cause the direction of the management or policies of a person or entity or the ownership of at least 7% of an entity either directly or indirectly.
(b) "Affiliate wheeling" means a person's use of direct access service where an electric utility delivers electricity generated at a person's industrial site to that person or that person's affiliate at a location, or general aggregated locations, within this state that was either 1 of the following:
(i) For at least 90 days during the period from January 1, 1996 to October 1, 1999, supplied by self-service power, but only to the extent of the capacity reserved or load served by self-service power during the period.
(ii) Capable of being supplied by a person's cogeneration capacity within this state that has had since January 1, 1996 a rated capacity of 15 megawatts or less, was placed in service before December 31, 1975, and has been in continuous service since that date. A person engaging in affiliate wheeling is not an electric supplier, an electric utility, or conducting an electric utility business when a person engages in affiliate wheeling.
(9) The rights of parties to existing contracts and agreements in effect as of January 1, 2000 between electric utilities and qualifying facilities, including the right to have the charges recovered from the customers of an electric utility, or its successor, shall not be abrogated, increased, or diminished by this act, nor shall the receipt of any proceeds of the securitization bonds by an electric utility be a basis for any regulatory disallowance. Further, any securitization or financing order issued by the commission that relates to a qualifying facility's power purchase contract shall fully consider that qualifying facility's legal and financial interests.
(10) The commission shall, after a contested case proceeding, issue annually an order approving for each electric utility a true-up adjustment to reconcile any overcollections or undercollections of the preceding 12 months to ensure the recovery of all amounts of net stranded costs. The rates for customers remaining with an incumbent electric utility will not be affected by the true-up process under this subsection. The commission shall review the electric utility's stranded cost recovery charges and securitization charges implemented for the preceding 12 months, and adjust the stranded cost recovery charge, by way of supplemental surcharges or credits, to allow the netting of stranded costs.
(11) The commission shall consider the reasonableness and appropriateness of various methods to determine net stranded costs, including, but not limited to, all of the following:
(a) Evaluating the relationship of market value to the net book value of generation assets and purchased power contracts.
(b) Evaluating net stranded costs based on the market price of power in relation to prices assumed by the commission in prior orders.
(c) Any other method the commission considers appropriate.
(12) The true-up adjustment adopted under subsection (10) shall not result in a modification to the securitization charge. The commission shall not adjust or change in any manner securitization charges authorized by the commission in a financing order issued under section 10i as a result of its review and any action taken under subsection (10).
(13) After the time period described in section 10d(2), the rates for retail customers that remain with or leave and later return to the incumbent electric utility shall be determined in the same manner as the rates were determined before the effective date of this section.
This act is ordered to take immediate effect.
Clerk of the House of Representatives
Secretary of the Senate
Approved
Governor