Fiscal Analysis

Southwestern MichiganCollege

Project Cost Increase

Bill/Sponsor

SCR 48, Senator Jelinek

House Committee

Appropriations

Analysis

Summary

The Information Technology Center Renovation capital outlay project forSouthwesternMichiganCollege was authorized under PA 297 of 2005.  The total authorized cost was established at $4,500,000 to be financed equally between State Building Authority bonds andSouthwesternMichiganCollege funds.  This multi-component project was to entail the renovations of its M-TECH Facility and theInformationTechnologyCenter.

Due to unanticipated inflationary increases, the college requests a project cost increase of $547,700 and, also to reduce the scope of the project to eliminate the M-TECH renovations.  The college will finance the entire cost increase.

The Joint Capital Outlay Subcommittee (JCOS) approved this resolution, with recommendation.  The Department of Management and Budget also recommends approval.

State Fiscal Impact

None

Local Fiscal Impact

SouthwesternMichiganCollege will finance the entire cost increase

SouthwesternMichigan College – Information Technology Center Renovation

Current Authorizations

Requested

Change

Revised

Authorizations

StateBuilding Authority

$2,249,800

$0

$2,249,800

State GF/GP

200

0

200

Southwestern Michigan

2,250,000

547,700

2,797,700

Totals

$4,500,000

$547,700

$5,047,700

Analyst(s)

Al Valenzio

Mitchell Bean, Director - House Fiscal Agency