CAPITAL OUTLAY APPROPRIATIONS                                             S.B. 78 (S-7):

                                                                      SUMMARY OF SUBSTITUTE BILL

                                                                                              IN COMMITTEE

 

 

 

 

 

 

 

 

Senate Bill 78 (Substitute S-7)

Sponsor:  Senator Ken Horn

Committee:  Appropriations

 


CONTENT

 

The bill would appropriate $2,900 for 29 $100 capital outlay project planning authorizations. Eleven of these planning authorizations would be for projects at universities and 18 would be for community colleges. A list of these projects is provided in Table 1. If each of these projects were provided with a construction authorization as written, the total cost of the projects would be $803.7 million, of which $447.1 million would be funded by the State through the issue of State Building Authority (SBA) bonds, and $356.6 million would come from matching funds from the universities and community colleges receiving the projects.

 

The bill also would appropriate $250.0 million General Fund/General Purpose for a new Student and Talent Attraction and Retention Grant Program that would be administered by the Department of Technology, Management and Budget (DTMB). The Program would provide grants of up to $4.0 million for each community college and university that received a capital outlay planning authorization in the bill, and $6.0 million for those that did not. These grants would be allowed to be used for capital and student housing improvements and/or the purchase of technology or other equipment that would accomplish any of the following:

 

·        Improve education outcomes for low-income students.

·        Improve the health or safety of students, faculty, or others on campus.

·        Improve student retention or increase enrollment.

 

Six months after receipt of the first grant application under the program, the DTMB would be required to issue a second round of grants with any remaining unspent or unobligated funds. No single institution would be allowed to receive a grant for more than 15.0% of any remaining funds under the second round of grants. Finally, the bill would establish the grant program as a work project, allowing funds to be spend through September 30, 2027.

 

The Governor did not recommend planning authorizations for any capital outlay project funded through the SBA in her fiscal year (FY) 2022-23 budget recommendation; however, all but one of the projects were reviewed, scored, and ranked by the State Budget Office (SBO). The project request that was not part of the SBO ranking process was the one for University of Michigan – Flint, which is a new request included in the bill. Three project requests (University of Michigan – Ann Arbor, Kellogg Community College, and Muskegon Community College) were not initially scored and ranked as they were deemed ineligible for SBA financing as submitted. The University of Michigan – Ann Arbor project has since been amended to make it eligible for SBA financing and is included in the bill. The other two unranked projects are not included in the bill.

 

 

 

 

 

FISCAL IMPACT

 

The bill contains 29 $100 planning authorization line items so, strictly speaking, the fiscal impact of those projects would be limited to $2,900, plus any planning costs incurred by universities and community colleges that would receive a planning authorization under the bill. Section 242(9) of the Management and Budget Act specifies that an appropriation for a planning authorization does not represent a commitment by the Legislature to provide funds for the construction of a project, but for projects that eventually receive a construction authorization, the State would cover a portion of those planning costs. If all of the projects in the bill were given construction authorizations at their requested State share levels, the SBA would finance about $447.1 million of the total $803.7 million cost of the projects through bonding. These additional bonds would increase SBA rent payments (debt service) in the Department of Treasury by an estimated $30.0 million to $50.0 million annually. The actual SBA rent costs could vary significantly depending on bond market conditions if and when the projects ultimately receive final SBA financing following completion of the projects.

 

Because of recent increases in construction costs, it is likely that the total actual cost of the projects in the bill could eventually exceed the total authorized project costs listed in the bill. If this were to happen, each institution that had those excess costs would have to seek a cost adjustment approval in a supplemental appropriations bill. If approved, the institution would be responsible for 100% of those increased costs. An institution that did not wish to increase its financial obligation for its project could alternately elect to seek a reduction in the scope of its project using the same process as a cost adjustment.

 

Finally, the bill would appropriate $250.0 million for grants to universities and community colleges for technology, equipment, and capital improvements as a one-time appropriation.

 

Table 1

SB 78 (S-7) Capital Outlay Planning Authorizations

University

Project

Total Cost

State Share1

Institution Share

Rank2

Central

Brooks Hall Renovation

$29,800,000

$22,350,000

$7,450,000

10

Eastern

Engineering and Technology Complex - Phase II - Roosevelt Hall

42,500,000

30,000,000

12,500,000

1

Ferris

Center for Interprofessional Health Sciences Education

29,500,000

22,125,000

7,375,000

4

Grand Valley

Blue Dot Lab

75,000,000

29,900,000

45,100,000

9

Lake Superior

Experiential Learning Center

25,000,000

18,750,000

6,250,000

8

Michigan Tech

Center for Convergence and Innovation - Phase I

70,000,000

29,900,000

40,100,000

2

Northern

Northern Enterprise Center (College of Business)

19,100,000

13,370,000

5,730,000

5

Oakland

Science Complex Renovation Project

40,000,000

30,000,000

10,000,000

3

University of Michigan – Ann Arbor

428 Church Street Building Renovation

50,000,000

37,500,000

12,500,000

Unranked

University of Michigan - Flint

College of Innovation and Technology

40,000,000

30,000,000

10,000,000

Unranked

Western

IF-1 Knauss Hall Renovation and Addition

30,000,000

22,500,000

7,500,000

11

Subtotal Universities.................................

$450,900,000

$286,395,000

$164,505,000

Community College

Project

Total Cost

State Share1

Institution Share

Rank2

Alpena

Charles R. Donnelly Natural Resources and STEM Innovation Center

$8,500,000

$4,250,000

$4,250,000

8

Bay de Noc

Manufacturing Hub and Safety Training Center

1,675,000

837,500

837,500

11

Glen Oaks

South Campus Renovation

7,000,000

3,500,000

3,500,000

5

Grand Rapids

Learning Resource Center Renovation & Expansion

32,000,000

16,000,000

16,000,000

15

Henry Ford

Energy Learning Center

11,600,000

5,220,000

6,380,000

13

Jackson

STEM Remodel of James McDivitt Hall

45,000,000

22,400,000

22,600,000

14

Kalamazoo Valley

Automotive Technology/Advanced Manufacturing Wing

39,000,000

19,500,000

19,500,000

16

Kirtland

Improved Programming for the Trades at Kirtland - Gaylord

7,186,100

3,593,000

3,593,100

17

Lake Michigan

Niles Campus Renovation & Upgrade

8,600,000

4,300,000

4,300,000

3

Monroe

Renovation and Addition to Welch Health Education Building

13,100,000

6,550,000

6,550,000

4

Mott

Prahl College Center Renovation

25,000,000

12,500,000

12,500,000

9

North Central

Career and Technical Education Enhancement (CATEE) Complex

9,141,000

4,570,500

4,570,500

2

Northwestern

Student Learning Support Services Renovation Project

5,000,000

2,500,000

2,500,000

6

Oakland

Skilled Trades and Industrial Tech. Building Renovation/Expansion

60,000,000

15,000,000

45,000,000

1

Schoolcraft

Forum Building Renovation and Expansion for Sciences and Fine Art

33,450,000

16,725,000

16,725,000

18

Southwestern

Dale A. Lyons Classroom Building Renovation

12,000,000

6,000,000

6,000,000

12

Washtenaw

Center for Success

23,000,000

11,500,000

11,500,000

7

Wayne

Center for Virtual Learning and Digital Careers

11,564,200

5,782,100

5,782,100

10

Subtotal Community Colleges..................

$352,816,300

$160,728,100

$192,088,200

Grand Total................................................

$803,716,300

$447,123,100

$356,593,200

1For universities, the State share reflects a 75% State match, limited to $30.0 million by DTMB policy. The State share for community college projects is 50%.

2Total State funding rank for capital outlay projects financed through the State Building Authority.

U of M - Flint's project is marked as "unranked" as it was not submitted during the normal priority project process.

U of M – Ann Arbor’s project is marked “unranked” as the project as submitted would not have been eligible for bond financing through the SBA. The University has since amended the project request to make it eligible for SBA financing.

 

Date Completed:  9-28-22                                        Fiscal Analyst:  Josh Sefton

 

This analysis was prepared by nonpartisan Senate staff for use by the Senate in its deliberations and does not constitute an official statement of legislative intent.